City of Gladwin Bike Path Project
Reilly Contracting's highlighted project is the City of Gladwin Bike Path Project completed in summer of 2024. Reilly contracting was the successful bidder for this 4500 ft long project and began clearing operations in spring of 2024. This $350,000.00 project took Reillys crew only 6 weeks to complete. 2,000 Cyd's of overburden was removed 4000 Cyd's of sand subbase, 2000 Cyd's of gravel, 350 Tons of Asphalt and 1500 Cyd's of topsoil were brought in to create a new bike path through a section of low-lying property owned by the city. Nine new culverts and 7500 ft of silt fence were also placed to maintain positive drainage and erosion control. Reillys crews completed this project a month ahead of schedule. Great, smart and productive employees and subcontractor relationships make Reilly Contracting the right company for the job.